Dear Murasato / Hanz Corporation
Thank you for your cooperation on GOLAR LNG FSRU and Nikkios-Posco Project
We would like to propose some design changes and to confirm some details.
The detail is below.
Regarding Nikkios-Posco Project
1. Please confirm that pad plate of skid rtd mounting pad will be applied to 10t instead of shell th’k
2. If required, please confirm location of lifting lug.
Regarding GOLAR LNG FSRU Project
3. We have not received documents(S2031) for DNV’s approval yet.
Common requests
4. Please inform the address of destination for hard copy.
We look forward to your favorable reply.
Your sincerely.
Younggun