• Documents included in the KBR Engineering requisition and the information contained shall not be copied or used for another than the purposes for which it is or has been provided in any form or medium to third parties except as expressly permitted by KBR.
• The technical information is subject to U.S. Export Control Regulations and it may not be
exported or re-exported except as authorized under applicable U.S. Export Control
Requirements.
• Receipt of major materials –
Tube & Pipe (for inner and outer tube) – 1st week of June
Manifold Pipe (and other misc pipe) – 3rd week of April
Forgings (for upper & lower, weldolets, clean out & drain nozzles – 3rd week of May
Cast Fittings - inlet castings & 90-Degree elbows – 1st week of July
Plate material – 3rd week of April
Structural Steel – 3rd week of March
• Machining work - start by 2nd week of May.
• Fabrication start
Parts Fabrication – 2nd week of March
Inner & Outer Tube Fab – 1st week of June
PQE sub assembly (inner & outer tube assembly) – 2nd week of July
Final assembly – (PQE + manifold assembly) – 3rd week of July
• Final Inspection (Dimensional, Visual, & Testing) – start by 4th week of July
• Support Structure Fabrication – start 3rd week of March